AMS Microchip Plant
In just 11 months of construction, a microchip plant with an attached office building was built in the greater Graz area. We took new paths, both conceptually and in terms of the chosen planning process (Design-Build-Project).






© ATP architects engineers

© ATP architects engineers

© ATP architects engineers

© ATP architects engineers

© ATP architects engineers
All functional and production areas are combined by a silver dynamic cladding element, whose significant form has become the new identifier for the entire site. A structural special feature: The roof assembly was completed up to a watertight roof using large wooden panel elements (l x w = 14.5 x 2.5 m) in just two weeks.
- Client
austria microsystems AG
- Location
Unterpremstätten/Graz, AT
- Construction Start
07/2000
- Completion
06/2001
- Gross Floor Area
17,400 m2
- Cleanroom Area
3,850 m2
- Gross Building Volume
99,300 m3
- Awards
1st Prize, Styrian Spengler Award 2001